Wings

Wings - Construction Log

Spars and Ribs (click on any date)
   
Hours:
June 15, 2007 Picked up my Wing Kit from Van's!
n/a
June 16, 2007 Wing Kit Inventory
3.0
June 18, 2007 Began Wing Construction
3.0
June 19, 2007 Riveting Platenuts
5.0
June 20, 2007 Countersinking, Countersinking, and Painting
4.5
June 24, 2007 Fabricating the Tie-Down Assembly
5.5
June 25, 2007 Finished the Tie-Down Assemblies
5.5
June 26, 2007 Started Rear Spar Assemblies
1.25
June 27, 2007 More Rear Spar Work
5.5
June 28, 2007 Rear Spar Work Continues
4.5
June 30, 2007 Finished the Rear Spars!
3.5
July 3-28, 2007 Preparing the Wing Ribs
39.0
July 31, 2007 Putting it all Together
4.0
August 3, 2007 Began cleaning the ribs for priming
1.5
August 4, 2007 Finished cleaning ribs, primed them, riveted left wing
11.0
August 5, 2007 Clecoed right wing ribs to spar, mounted on blocks
1.0
August 6, 2007 Finished riveting right wing skeleton
4.25
 
Sub-total hours:
102.0

Left Wing Work
   
Hours:
August 12, 2007 Built cradle, assembled Left Leading Edge
5.0
August 23, 2007 More leading edge work
4.5
August 29, 2007 Trip to Van's
n/a
September 2, 2007 Started on the Landing lights, help from Dad
3.0
September 3, 2007 Built Wing Stand
6.0
September 5, 2007 More leading edge work
6.5
September 6, 2007 Finished dimpling, riveted leading edge together
6.0
September 7, 2007 Wing Stand alignment; skins clecoed on
4.0
September 10, 2007 Made the doubler; clecoed skins on
2.0
September 30, 2007 Finished alignment & clamps; drilled top skins
6.0
October 1, 2007 Drilled bottom skins; finished leading edge
5.0
 
Sub-total hours:
48.0

Left Tank
   
Hours:
October 2, 2007 Started on the Left Tank
3.0
October 5, 2007 Prepared z-brackets, fitted tank to wing
7.0
October 6, 2007 Drilled z-brackets, splice plate
6.0
October 8, 2007 Drilled the tank, primed parts, Duckworks light
5.0
October 10, 2007 Countersunk main spar rivet holes
1.5
October 11, 2007 Removed vinyl strips from tank skin
1.5
October 12, 2007 Countersunk tank skin, lots of deburring, stiffeners
6.0
October 13, 2007 Drilled skin to stiffeners, deburred, drain, fuel cap
6.0
October 14, 2007 Tank attach brackets, dimpling, countersinking
4.0
October 21, 2007 Drilled attach brackets, stiffener plates
3.0
October 22, 2007 New Toys!
n/a
October 26, 2007 Fun with Dangerous Tools
3.5
October 27, 2007 Riveting on Nutplates
1.5
October 30, 2007 Trip to Van's - Work on New End Rib
1.5
November 1, 2007 Scuffing inside of skins - lost my compressor!
1.5
November 2, 2007 New Compressor, worked on tank prep for riveting
9.0
November 9, 2007 Started Riveting Tank Ribs
7.5
November 10, 2007 More riveting and sealing tank ribs
10.0
November 15, 2007 Last 2 Ribs Riveted and Sealed
7.5
November 17, 2007 Plumbing inside the Tank
6.0
November 21, 2007 Fuel Float Gauge
2.0
November 23, 2007 Tank Cover Plate
5.0
November 24, 2007 Installed Fuel Float Gauge
4.0
November 26, 2007 Final prep before closing tank
2.0
November 28, 2007 Closed tank, riveted baffle end plate on
6.0
 
Sub-total hours:
110.0

Finishing up the Left Wing
   
Hours:
November 29, 2007 Fitting the leading edge/tank joint
1.5
December 1, 2007 Final fitting and finishing the tank
8.0
December 2, 2007 Duckworks Landing Light
3.0
December 3, 2007 Leak Testing the Tank!
1.5
December 4, 2007 Finished Landing light, preparing tools for riveting
1.5
December 8, 2007 Preparing Wing Skins for final assembly
7.5
December 9, 2007 Dimpled Lots of Ribs
1.5
December 11, 2007 Work on Top Inboard Skin
1.0
December 14, 2007 More Work on Top Skins
4.5
December 15, 2007 Deburring and dimpling ribs, rear spar
3.0
December 27, 2007 Riveted Leading edge to the spar
6.0
December 29, 2007 Bolted on the Tank; installed pitot tube
7.5
December 30, 2007 More work on Pitot Tube
1.0
January 5, 2008 Primed scarf joints, riveted top wing skins on!
8.5
 
Sub-total hours:
56.0

Right Wing Work
   
Hours:
January 9, 2008 Pulled left wing off jig, mounted right skeleton on
6.0
January 10, 2008 Attached and Drilled Wing Skins
6.5
January 13, 2008 Leading Edge End Rib, Splice Plate
7.5
January 16, 2008 Duckworks landing light
1.0
January 17, 2008 Duckworks landing light - continued
2.0
January 19, 2008 Finished Duckworks landing light
6.0
January 20, 2008 Started Riveting Leading Edge
1.0
January 25, 2008 Finished Leading Edge, Clecoed Tank Together
5.5
 
Sub-total hours:
35.5

Right Tank
   
Hours:
January 30, 2008 Drilled z-brackets to the spar
1.5
February 1, 2008 Deja Vu - z-brackets, rivets & platenuts, and a tank
7.0
February 2, 2008 Lots of Drilling
4.0
February 6, 2008 Wrapping up some leading edge details
4.0
February 8, 2008 Back to work on the tank
4.25
February 10, 2008 More work on the tank skin
2.5
February 11, 2008 Deburring holes and edges
0.75
February 12, 2008 More deburring, then dimpling
2.5
February 14, 2008 Finished dimpling
1.5
February 16, 2008 Scuffing everything up
1.5
February 17, 2008 Started Assembling and Sealing the Tank
6.0
February 18, 2008 Riveted Stiffeners, Fuel Cap Flange, Drain Flange
6.0
February 24, 2008 First ribs go into the right tank
1.5
February 26, 2008 Riveting and sealing ribs
5.0
February 27, 2008 Riveting and sealing ribs - continued
5.0
March 1, 2008 Sealing ribs into place
3.0
March 2-4, 2008 Riveting and sealing ribs
3.5
March 5, 2008 Finished riveting and sealing ribs
6.5
March 7, 2008 Installed vent line, fuel tube, worked on z-brackets
4.0
March 8, 2008 Fitted the fuel float gauge
2.0
March 9, 2008 Installed and sealed the baffle plate
7.0
March 10, 2008 Installed and sealed access cover plate
2.0
March 11, 2008 Pressure testing the tank
1.0
March 13, 2008 Pressure test passed - TANK FINISHED!
n/a
 
Sub-total hours:
82.0

Finishing up the Right Wing
   
Hours:
March 22, 2008 Fitted the leading edge/tank joint; riveted it on
3.0
March 26, 2008 More work on leading edge/tank joint; bolted on tank
4.0
March 28, 2008 Ribs - deburring dimpling, countersinking rear spar
6.0
March 29, 2008 Fixing a Tool Problem - scotchbrite wheel
n/a
April 9-27, 2008 Wing work continues
31.0
April 29, 2008 Broken Rivet Set Tool; Finished access cover plates
2.0
April 30, 2008 Left Outboard Aileron Bracket - deburred & drilled
1.0
 
Sub-total hours:
47.0

Ailerons
March 30, 2008 Set up band saw, cut aileron stiffeners
2.0
April 30, 2008 Aileron Bracket - left outboard; drilled & deburred
1.0
May 1-4,2008 Work on ailerons continues over several days
10.0
May 9, 2008 Priming and riveting
6.0
May 10, 2008 More riveting, moving on
6.5
May 11, 2008 Aileron Stiffeners - drilling, deburring, dimpling
4.0
May 12, 2008 Philip helps me! Deburred, dimpled, primed, riveted
3.5
May 13, 2008 Riveting and deburring skins. Bending brake problem
2.5
May 14, 2008 New bending brake. Bent skins. Drilled stiffeners
3.5
May 15, 2008 Drilled stiffeners to left aileron, drilled skin to spar
2.0
May 18-22, 2008 Work on the aileron spars & stiffeners
10.0
May 23, 2008 Assembly of complete ailerons, drilling, etc.
3.0
May 25, 2008 Aileron work continues. Details, details.
3.0
May 30, 2008 Worked on nose skin problem. Dimpled leading edge
6.0
May 31, 2008 Primed all remaining parts. Built riveting jig. Riveted.
6.0
June 1, 2008 Finished riveting the ailerons!
3.0
June 5, 2008 Finished installing the Brackets, mounted ailerons!
2.0
 
Sub-total hours:
74.0

Flaps
June 7-10, 2008 Started on the Flaps
4.5
June 13, 2008 More skin drilling, work on hinges and brackets
3.0
June 16, 2008 Fabricating the flap brackets
0.5
July 1-3, 2008 Drilling flap hinge for rt. flap, Bending the brackets
4.5
July 5-6, 2008 Drilling flap brackets, countersinking spars, deburring
5.0
July 8-9, 2008 Deburring, dimpling, priming, started riveting
5.5
July 10, 2008 Preparing flap skins - deburring, scuffing, cleaning
3.5
July 12, 2008 Finished prep work, primed skins, started riveting
5.5
July 14, 2008 Assembled the Flaps, made V-blocks
2.5
July 16, 2008 More riveting on the Flaps, finished left flap
2.5
July 18-20, 2008 Finishing up the Flaps!
4.5
 
Sub-total hours:
41.5

Interior Wing Details, Closing up the Wings
July 23, 2008 Aileron pushrods
4.5
July 25, 2008 Aileron Bellcrank Bushings
1.0
July 28, 2008 Bellcrank bushing - continued
2.0
August 1, 2008 Installing bellcranks, attaching ailerons
5.0
August 4, 2008 Finished Ailerons, mounting Flaps
4.0
August 19, 2008 Wing Plumbing; Pitot Tube
4.5
August 20, 2008 Trip to Advanced Flight Systems
0.0
August 24, 2008 Installing A.O.A. System "A" kit
2.5
August 26, 2008 A.O.A. kit - continued
3.0
August 31, 2008 Started riveting bottom skin - left wing
3.0
September 1, 2008 Bottom skin riveting - continued. Access cover plates
4.0
September 2, 2008 Finished riveting left wing bottom skins!
7.0
September 4-7, 2008 Cleaned up left wing, back in storage cradle, details
11.0
September 8, 2008 Installed Tru-Track autopilot brackets; riveting
3.0
September 9, 2008 More riveting, with Daniel
1.0
September 10, 2008 More riveting, finished bottom inboard skin, flap hinge
4.0
September 11, 2008 Finished riveting. WINGS FINISHED!!
4.5
 
Sub-total hours:
64.0
     
 
TOTAL HOURS FOR THE WINGS:
660.0 
 
Total Project Hours:
881.5