Finishing Kit

Finishing Kit - Construction Log

Preparing for the Tip-Up Canopy Installation (click on any date)
April 15, 2011 Picked up Finishing Kit from Vans!
Hours:
April 16-17, 2011 Inventory, rearranging and cleaning up the Shop
5.0
April 24, 2011 Work Begins on the Canopy Frame Hinge Pin Blocks
3.0
April 27, 2011 Canopy Hinge Pin Blocks - continued
4.0
May 1, 2011 Aft Canopy Latch Mechanism
4.0
May 8, 2011 The Forward Canopy Frame
7.0
May 15, 2011 The Canopy Release Mechanism
8.0
May 18, 2011 Aft Canopy Latch - continued
3.0
May 19, 2011 The Canopy Frame - continued
2.0
May 20, 2011 The Canopy Frame - continued
2.0
May 28, 2011 The Canopy Frame - continued
6.5
June 7-8, 2011 Drilling the Hinges
2.5
June 19, 2011 The Canopy Release Mechanism - continued
4.0
June 21, 2011 Finished drilling Hinges, more Canopy Release work
6.5
July 1-4, 2011 Canopy Frame Fitting & More Prep Work
11.0
July 6, 2011 Fitting the Aft Canopy Framp Parts
4.5
July 13, 2011 Fitting Aft Canopy Framp Parts - continued
5.0
July 23, 2011 Final Fitting and Drilling, etc. Visit to Vans!
10.0
July 24, 2011 Canopy Frame Prep Work
4.0
July 25, 2011 Drilling, Fabricating Wedges
2.0
July 26, 2011 Canopy Frame Final Assembly (for now)
3.0
July 28, 2011 Putting it all together, and back on the plane
2.0
 
Sub-total hours:
103.0

The Canopy
July 29-30, 2011 Taping, and Prep Work, Fabricating Tail Stand
4.0
August 4, 2011 Big Blunder - CRACKED CANOPY
2.5
August 5, 2011 Daryl and Scott at Vans - to the Rescue
5.0
August 7, 2011 Canopy Trimming
4.5
August 11, 2011 Canopy Trimming Continues
2.5
August 12, 2011 The Big Cut!
2.0
August 13, 2011 Canopy Trimming and Marking
4.0
August 15, 2011 More Canopy Trimming, Trimmed the "ears"
4.0
August 23-24, 2011 The Second "Big Cut", More Fitting Work .
5.0
August 25, 2011 Canopy Frame Work - Finishing Details
4.5
August 27, 2011 Canopy Brace Kit - work begins
3.0
August 28-29, 2011 Brace Kit deburring; Fabricating Strut Parts
5.0
August 30, 2011 The Tipup Canopy Frame Struts
5.0
August 31, 2011 The Canopy Frame Brace Kit
4.0
September 4, 2011 Canopy Frame Brace Kit - Continued
3.0
September 6, 2011 Canopy Frame Brace Kit - Continued
3.0
September 7, 2011 Canopy Frame Brace Kit - Continued
3.0
September 24, 2011 The Canopy Frame - Painting
3.0
September 25, 2011 The Canopy Frame - Riveting
2.0
November 13, 2011 New JD Air Parts Canopy Latch
7.5
December 28, 2011 Final trimming on Canopy; Canopy Side Skirts
6.0
December 31, 2011 Canopy Side Skirts - Continued
4.0
January 26, 2012 Final Canopy Trimming and Deburring
3.0
January 28, 2012 Canopy Latch - Initial Installation
5.0
February 4, 2012 Bulkhead Covers - Paint Prep
4.5
February 12, 2012 Painting Session
3.5
February 17, 2012 Upper Canopy Latch Handle
2.5
February 19, 2012 Installing the Canopy Lift Struts
3.0
February 25, 2012 Forward Canopy Stops
8.0
March 1, 2012 Back to the Canopy Latch
4.0
March 11, 2012 Painting Details, Canopy Latch Lock!
6.0
March 14, 2012 Riveted Canopy Latch Handles in Place
2.0
March 17, 2012 The Glare Shield - Fitting the Vinyl Covering
4.5
March 18, 2012 Another Painting Session
3.0
March 23, 2012 Glare Shield continued - Final Vinyl Trimming
2.0
April 13, 2012 Glare Shield continued - Application of Vinyl
4.0
April 20, 2012 Final Prep on the Canopy and Frame
4.5
April 21, 2012 The Big Day - SikaFlex the Canopy in Place!
6.0
April 22-29, 2012 Canopy SikaFlex Installation - page 2
9.0
June 24, 2012 Canopy Fairing - Work begins!
8.0
June 27, 2012 Canopy Fairing Work - continued
3.0
June 30, 2012 Canopy Fairing Work - continued
3.0
July 1, 2012 Canopy Fairing Work - continued
3.0
July 3, 2012 Canopy Fairing Work - continued
2.0
July 4, 2012 Canopy Fairing Work - continued
3.0
July 10, 2012 Canopy Fairing Work - continued
5.0
July 14, 2012 Canopy Fairing Work - continued
5.0
July 16, 2012 Canopy Fairing Work - continued
2.0
July 17, 2012 Canopy Fairing FINISHED! (I think)
2.0
July 22, 2012 Canopy Frame Latch Lugs Installed
5.0
   
 
Sub-total hours:
202.0

Miscellaneous Items & Sub-Projects
April 23, 2011 Fixing a Problem with my Wings
4.0
February 18, 2012 Axle Nut Wrench - Kit from Vans
1.0
February 29, 2012 My Airplane has SEATS!!
n/a
March 19, 2012 The Map Box
3.0
March 25, 2012 The Map Box - page 2
12.0
April 14, 2012 The Canopy Jettison Handle
6.0
April 15, 2012 Riveting the Sub-Panel to the Fuselage
5.0
April 24, 2012 The Nosewheel Assembly
14.0
April 28, 2012 The Air Vents
7.0
June 9, 2012 The Main Wheels
8.0
August 4 & 5, 2012 Pitch Servo Install; Engine Mount Prep Work
2.0
September 13, 2012 Pitch Servo - continued, Roll Servo, too!
5.0
September 15, 2012 Engine Mount Installed!
4.0
September 30, 2012 The Main Wheels - continued
3.0

Top Fuselage Skin and Rear Window Installation
October 19, 2013 Canopy Guides on the Roll Bar
6.0
December 28, 2013 Riveting on the Top Aft Fuselage Skin
7.0
January 4, 2014 Installing the Rear Window - Prep Work begins
5.0
January 5, 2014 Installing the Rear Window - Installation!
5.0
January 6, 2014 Installing the Rear Window - Post-Installation - DONE!
2.0
January 7, 2014 Fixing the side skirt on the Tipup Canopy
11.0
   
 
TOTAL HOURS FOR FINISHING KIT:
414.0
 
Total Project Hours:
2,365.0